Construction Updates

January 2026


North Tank Farm:

  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings on campus
  • Placing / grading / compacting infill soil

South Tank Farm:

  • Demolition of underground bunker tanks
  • Soil remediation
  • Placing / grading / compacting of infill soil

Marine Dock:

  • Cleaning of pipelines
  • Demolition of dock equipment and structures

Milestones

  • 28 of 29 above ground storage tanks demolished
  • 14 of 18 Bunker tank demolished
  • 94,715 linear feet of pipeline removed

December 2025

North Tank Farm:

  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings on campus
  • Placing / grading / compacting infill soil

South Tank Farm:

  • Demolition of underground bunker tanks
  • Soil remediation
  • Placing / grading / compacting of infill soil

Marine Dock:

  • Cleaning of pipelines
  • Demolition of pipelines, dock equipment and structures


Milestones

  • 28 of 29 above ground storage tanks demolished
  • 14 of 18 Bunker tanks demolished
  • 90,125 linear feet of pipeline removed

November 2025

North Tank Farm:

  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings on campus
  • Placing / grading / compacting infill soil

South Tank Farm:

  • Demolition of underground bunker tanks
  • Soil remediation
  • Placing / grading / compacting of infill soil

Marine Dock:

  • Cleaning of pipelines
  • Demolition of dock equipment and structures

Milestones

  • 28 of 29 above ground storage tanks demolished
  • 14 of 18 Bunker tank demolished
  • 90,125 linear feet of pipeline removed

 

October 2025

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings on campus
  • Placing / grading / compacting infill soil

South Tank Farm:

  • Demolition of underground bunker tanks
  • Soil remediation
  • Placing / grading / compacting of infill soil

Marine Dock:

  • Cleaning of pipelines
  • Demolition of dock equipment and structures

Milestones

  • 28 of 29 above ground storage tanks demolished
  • 14 of 18 Bunker tank demolished
  • 51,223 linear feet of pipeline removed

September 2025

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings on campus
  • Demolition of buildings along Beacham Street
  • Placing / grading / compacting infill soil

South Tank Farm:

  • Purging of pipelines
  • Demolition of underground bunker tanks
  • Soil remediation
  • Placing / grading / compacting of infill soil

Marine Dock:

  • Cleaning of pipelines

Milestones

  • 27 of 29 above ground storage tanks demolished
  • 14 of 18 Bunker tank demolished
  • 51,223 linear feet of pipeline removed

August 2025

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings on campus
  • Demolition of buildings along Beacham Street
  • Placing / grading / compacting infill soil

South Tank Farm:

  • Purging of pipelines
  • Demolition of underground bunker tanks
  • Soil remediation
  • Placing / grading / compacting of infill soil

Marine Dock:

  • Cleaning of pipelines

Milestones

  • 27 of 29 above ground storage tanks demolished
  • 11 of 18 Bunker tank demolished
  • 51,223 linear feet of pipeline removed

July 2025

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings on campus
  • Demolition of buildings along Beacham Street
  • Placing / grading / compacting infill soil

South Tank Farm:

  • Purging of pipelines
  • Demolition of underground bunker tanks
  • Soil remediation
  • Placing / grading / compacting of infill soil

Marine Dock:

  • Cleaning of pipelines

Milestones

  • 27 of 29 above ground storage tanks demolished
  • 11 of 18 Bunker tank demolished
  • 51,223 linear feet of pipeline removed

June 2025

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings on campus
  • Demolition of buildings along Beacham Street
  • Placing / grading / compacting infill soil

South Tank Farm:

  • Purging of pipelines
  • Demolition of underground bunker tanks
  • Soil remediation
  • Placing / grading / compacting of infill soil

Marine Dock:

  • No planned work

Milestones

  • 27 of 29 above ground storage tanks demolished
  • 9 of 18 Bunker tank demolished
  • 51,223 linear feet of pipeline removed

May 2025

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings on campus
  • Demolition of buildings along Beacham Street
  • Placing / grading / compacting infill soil

South Tank Farm:

  • Purging of pipelines
  • Demolition of underground bunker tanks
  • Soil remediation
  • Placing / grading/compacting of infill soil

Marine Dock:

  • No planned work

Milestones

  • 27 of 29 above ground storage tanks demolished
  • 9 of 18 Bunker tank demolished
  • 51,223 linear feet of pipeline removed

April 2025

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings on campus
  • Demolition of buildings along Beacham Street
  • Placing / grading / compacting infill soil

South Tank Farm:

  • Purging of pipelines
  • Purging of underground bunker tanks
  • Demolition of above grade pipe racks
  • Soil remediation
  • Placing / grading / compacting of infill soil

Marine Dock:

  • No planned work

Milestones

  • 27 of 28 above ground storage tanks demolished
  • 9 of 18 Bunker tank demolished
  • 47,860 linear feet of pipeline removed

 

March 2025

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings
  • Placing / grading / compacting infill soil

South Tank Farm:

  • Purging of pipelines
  • Purging of underground bunker tanks
  • Demolition of above grade pipe racks
  • Soil remediation
  • Placing / grading / compacting of infill soil

Marine Dock:

  • No planned work

Milestones

  • 26 of 28 above ground storage tanks demolished
  • 7 of 18 Bunker tank demolished
  • 47,860 linear feet of pipeline removed

 

February 2025

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings
  • Placing / grading / compacting infill soil
 

South Tank Farm:

  • Purging of pipelines
  • Purging of underground bunker tanks
  • Demolition of above grade pipe racks
  • Soil remediation
  • Placing / grading / compacting of infill soil
 

Marine Dock:

  • No planned work
 

Milestones

  • 26 of 28 above ground storage tanks demolished
  • 6 of 18 Bunker tank demolished
  • 26,600 linear feet of pipeline removed

January 2025

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings

South Tank Farm:

  • Purging of pipelines
  • Purging of underground bunker tanks
  • Soil remediation
  • 6 of 18 Bunker tank demolished

Marine Dock:

  • No planned work

Milestones

  • 26 of 28 tanks demolished
  • 26,600 linear feet of pipeline removed

 

December 2024

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings

South Tank Farm:

  • Purging of pipelines
  • Purging of underground bunker tanks
  • Soil remediation
  • 6 of 18 Bunker tank demolished

Marine Dock:

  • No planned work

Milestones

  • 25 of 28 tanks demolished
  • 26,600 linear feet of pipeline removed

November 2024

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation
  • Demolition of buildings

South Tank Farm:

  • Purging of pipelines
  • Purging of underground bunker tanks
  • Soil remediation
  • Bunker tank demolition

Marine Dock:

  • No planned work

Milestones

  • 24 of 28 tanks demolished
  • 26,600 linear feet of pipeline removed

October 2024

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation

South Tank Farm:

  • Purging of pipelines
  • Purging of underground bunker tanks
  • Soil remediation
  • Bunker tank demolition

Marine Dock:

  • No planned work

Milestones

  • 20 of 28 tanks demolished
  • 17,480 linear feet of pipeline removed
  •  

September 2024

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation

South Tank Farm:

  • Purging of pipelines
  • Purging of underground bunker tanks
  • Soil remediation
  • Bunker tank demolition

Marine Dock:

  • No planned work

Milestones

  • 18 of 28 tanks demolished
  • 16,779 linear feet of pipeline removed
  •  

August 2024

North Tank Farm:

  • Onsite utility disconnects
  • Purging of above ground storage tanks and pipelines
  • Demolition of above ground storage tanks
  • Soil remediation

South Tank Farm:

  • Purging of pipelines
  • Purging of underground bunker tanks
  • Soil remediation

Marine Dock:

  • No planned work

Milestones

  • 13 of 28 tanks demolishes
  • 16,000+ linear feet of pipeline removed
  •  